Construction updates as of Feb. 21

He is crafting something for Central Valley concerning safety that he wants ready before our students return from break.  Read the details below:

Fisher

Construction is on-time. All work to be completed by the start of school Sept. ’18

Completed to date:

  • New roofs
  • New boiler
  • Central office, including the main office, nurse’s suite, and faculty room
  • New secured entrance
  • Two renovated classrooms
  • Six-classroom addition with bathrooms
  • IT upgrades, including cabling, servers, technology rooms, and building-wide wireless

Complete Spring ’18

  • Conversion of three classrooms into new media center
  • New playground
  • Access roadway

Begin Summer ’18/Complete by ’18

  • Cafeteria and kitchen expansion and renovation
  • New student lockers
  • New hallway ceilings and LED lighting
  • New wall tiles in some corridors
  • Pave fire lane

Barringer Road

Construction is on-time. All work to be completed by the start of school Sept. ’18

Completed to date:

  • Roofs
  • Central office, including the main office and nurse’s suite
  • Renovation of former locker rooms into occupational therapy, physical therapy, speech and life skills classrooms.
  • Four-classroom addition with bathrooms and full basement storage

Ongoing work to complete Spring ’18

  • IT upgrades, including cabling, servers, technology rooms, and building-wide wireless
  • Conversion of classroom into chorus room
  • New hallway ceilings and LED lighting

Summer ’18 to complete by start of school Sept. ’18

  • Renovation of kitchen
  • New playground
  • Window upgrades
  • Pave fire lane
  • New main entrance façade

CVA

Despite delays waiting for steel from the manufacturer, contractors are on schedule to complete all work ahead of the start of school Sept. ’19.

Completed to date:

  • New district offices on Weber Ave.

Ongoing work to complete by start of school Sept. ’18

  • Addition, including kitchen, cafeteria, learning center, school entrance, main office

Summer to be completed by start of school Sept. ’18

  • Convert current main office into nurse’s suite
  • Renovate technology and art rooms
  • New turf sports field
  • Site work and paving parking areas
  • IT upgrades, including cabling, servers, technology rooms, and building-wide wireless

Summer ’19 to be completed by start of school Sept. ’19

  • Convert current cafeteria/kitchen into Family & Consumer Science classrooms and NJROTC space.

Jarvis

Complete renovation begins after July 4, 2018 to be completed by start of school Sept. ’20